Change order template: what goes in a construction change order

A construction change order is a written agreement, signed by the owner and contractor (and the architect on AIA contracts), that changes the work, the contract price, the contract time, or all three. A complete change order describes the change, prices it line by line, states the days added or removed, and carries the signatures. The template below lists every field.

Updated 2026-11-17

What a change order is, and what it is not

A change order is the signed record that both sides agree on a change. AIA A201-2017, Section 7.2.1, defines it as a written instrument signed by the owner, contractor and architect that states their agreement on three things: the change in the work, the amount of any adjustment to the contract sum, and the extent of any adjustment to the contract time. If one of those three is left blank, you do not yet have an agreement on it.

Other documents get confused with change orders. A change order request or proposal is your priced offer, not yet accepted. A construction change directive (A201 Section 7.3.1) is a written order from the owner and architect directing a change before price or time is agreed. A minor change (Section 7.4) is a change that does not touch price or time. Know which one you are holding, because only a signed change order settles the money and the days.

The standard forms

Many owners and architects use AIA's G-series forms. G701-2017 is the AIA Change Order form, G714-2017 is the Construction Change Directive, and G709-2018 is the Work Changes Proposal Request. Your contract may require a specific form or the owner's own. If it does, use it; the fields below still tell you what has to be on it.

On federal work the rules come from the contract clauses. Under FAR 52.243-4, Changes, the contractor must assert its right to an adjustment within 30 days after receiving a written change order, and for a change ordered other than in writing, the contractor must give written notice, and costs incurred more than 20 days before that notice are generally not recoverable. Read the changes clause in your own contract before work starts, not after.

How to price a change order

Price change orders the same way every time so the owner can check them and you can defend them. Break the cost into labor, material, equipment, subcontractor and other costs, then apply markup and any tax or bond your contract allows. A lump sum with no backup invites a fight; an itemized change order invites a review.

Include the cost of the time, not just the work. If the change extends the job, general conditions such as supervision, temporary facilities and equipment rental keep running. Many disputes come from a change order that priced the added work but stayed silent on the days, then a later request for extended general conditions that the owner says was already settled.

Schedule impact

State the time impact in days on every change order, even when it is zero. Write "0 days" rather than leaving it blank. Under A201, time is one of the three things a change order agrees on, so a signed change order with no time adjustment can be read as agreement that there was none.

If you cannot yet know the time impact, say so on the change order and reserve the right to request time, or ask for a construction change directive so the work can proceed while time is worked out. Check what your contract says about reservations, since some contracts limit them.

The change order process, step by step

Most change orders follow the same path. The steps that get skipped, usually written notice and signed approval before the work, are the ones that cause unpaid work.

Change orders between GCs and subcontractors

A change rarely stops at the prime contract. When the owner changes the work, the affected subcontractors need their own change orders, priced and signed under their subcontracts, and the notice deadlines in those subcontracts can be shorter than the prime contract's so the GC has time to pass a sub's request up the chain.

If you are a subcontractor, send your change order request to the GC with the same backup the owner will want to see: quantities, quotes, hours and days. If you are the GC, log every sub request against the owner change it belongs to, so nothing gets approved upstream and forgotten downstream, or paid downstream and never recovered upstream.

Common change order mistakes

Change order problems tend to repeat. Most of them come down to doing the work first and papering it later.

Change order template

Project name and numberMatch the contract.
Change order numberSequential per project. Never reuse a number.
DateDate issued for signature.
Contract partiesOwner, contractor and architect if any.
Reason for changeOwner request, design change, RFI answer, concealed condition. Reference the RFI or directive number.
Description of changeWhat is added, deleted or revised, with drawing and spec references.
Line itemsDescription, quantity, unit, unit cost and total for each item.
Labor, equipment and other costsHours and rates, equipment time, permits or fees.
Markup, tax and bondPercentages and amounts as allowed by the contract.
Change order totalNet add or deduct.
Original contract sumFrom the signed agreement.
Net change by previous change ordersSum of approved change orders to date.
New contract sumIncluding this change order.
Schedule impactDays added or removed. Write 0 if none.
New completion dateIncluding this change order.
AttachmentsQuotes, sketches, photos, RFI.
SignaturesOwner, contractor and architect, each with name, title and date.

How PILOTA handles this

PILOTA change orders have line items with quantity and unit cost plus labor, equipment and other costs, with markup, tax and bond filled in from your company settings. Each one records the days it adds to the schedule and moves from Draft to Pending to Approved or Rejected. You can send a change order to the client from the web portal to sign in their PILOTA client portal, and an approved change order is added to the project budget used by PILOTA job costing.

Frequently asked questions

A construction change order should include the project, a change order number, the reason for the change, a description with drawing references, itemized costs, markup, the new contract sum, the schedule impact in days and the signatures of every party the contract requires.

Under AIA A201-2017, a change order is signed by the owner, the contractor and the architect. Under other contracts, check who has authority to sign; a signature from someone without that authority may not bind the owner.

A change order is a signed agreement on the change, its price and its time. A construction change directive is a written order from the owner and architect to proceed with a change before price or time has been agreed.

Avoid it whenever you can. If the owner needs the work done now, get written direction, such as a construction change directive, and give any notice your contract requires before starting, so the cost and time can still be recovered.

The AIA change order form is G701-2017, Change Order. AIA also publishes G714-2017, Construction Change Directive, and G709-2018, Work Changes Proposal Request.