Construction punch list template and how the punch process works

A construction punch list is the list of work items that still have to be completed or corrected before a project, or a portion of it, can be closed out. Each item should say exactly where it is, what is wrong, which trade owns it, who is fixing it and by when, with a photo. The template below has every field you need to get items closed instead of argued about.

Updated 2026-11-17

Where the punch list fits in closeout

On AIA contracts the punch list is tied to substantial completion. A201-2017, Section 9.8.2, says that when the contractor considers the work, or a portion the owner agrees to accept separately, substantially complete, the contractor prepares and submits to the architect a comprehensive list of items to be completed or corrected before final payment. Leaving an item off the list does not change the contractor's responsibility to complete all the work.

The architect then inspects (Section 9.8.3). If the inspection finds items, on the list or not, that keep the owner from occupying or using the work for its intended purpose, the contractor fixes them and asks for another inspection. When the work is substantially complete, the architect prepares a Certificate of Substantial Completion (Section 9.8.4), which sets the date of substantial completion and the time within which the contractor must finish the items on the attached list. AIA's form for that certificate is G704-2017.

Start punching before the punch walk

The best punch lists are short because most items were caught earlier. Crews that walk their own work area by area, as each area finishes, find the missing cover plates, paint touch-ups and damaged trim while the trade is still on site. Waiting until the final walk means calling subs back from other jobs for small items, which is where closeouts drag on.

Run a pre-punch on each floor or area as finishes complete. Have each trade walk and clear its own items before the GC's walk, and the GC clear its list before the owner's or architect's walk. By the time the architect inspects, the list should be what's left, not what was never checked.

How to write a punch item that gets fixed

A punch item is an instruction to someone who was not standing next to you when you wrote it. "Fix door" will come back unfixed or fixed wrong. "Room 214, door 214A, closer leaking oil and door does not latch, Div 08 hardware, photo attached" sends the right person to the right door with the right tools.

Organize the list so it moves

One master list is the record, but nobody works from a 400-line spreadsheet. Sort and send the list by trade so each sub gets only their items, and by area so a superintendent can walk a floor and check items off. Track status for every item: open, in progress, ready for review, closed.

Review the open list on a set schedule, weekly or more often near turnover. Look at overdue items first. If one trade has most of the open items, that is a manpower conversation, not a list problem.

Closing items and closing the job

An item is closed when someone other than the person who fixed it has looked at it and agreed. Take an after photo. Keep who closed it and when. That record answers the question that always comes up at final payment: was this ever fixed?

Final payment usually depends on more than the punch list. Closeout typically also includes warranties, operation and maintenance manuals, as-built drawings, attic stock, final inspections and lien releases, depending on your contract. Put those on their own closeout checklist and run it in parallel with the punch list so the last punch item is not followed by a month of paperwork.

Running punch as a subcontractor

For a specialty contractor, the punch list is often the last thing standing between you and your retention. Ask the GC for your items as a separate list, by area, with photos, and confirm every item is actually yours before you send a crew. Items caused by another trade's damage should be flagged right away with a photo, so the cost goes to whoever caused it.

Plan the punch crew like any other phase. A small crew with the right material, a printed or phone list sorted by area, and authority to fix things on the spot will clear more items in a day than a larger crew that has to call the office for every question. When an item is done, send the after photo the same day and ask the GC to verify it, so your list shrinks on their log, not only on yours.

Common punch list problems

Most punch list delays trace back to the same handful of causes.

Punch list template

Item numberSequential per project.
ProjectName and number.
LocationBuilding, floor, room or gridline, and the element.
DescriptionWhat is wrong and what complete looks like.
TradeTrade or spec division responsible.
Assigned toCompany and person fixing it.
PriorityCritical (blocks occupancy or inspection), high, normal.
Date added and added byWho found it and when.
Due dateA specific date.
PhotosBefore photo when logged, after photo when fixed, each captioned.
StatusOpen, in progress, resolved, closed.
Resolved by and dateWho fixed it.
Verified by and dateWho checked it and closed it.

How PILOTA handles this

In PILOTA, punch items are tracked as Issues, each with a title, description, priority, project, location, trade, due date, assignee and captioned photos. Items move through Open, In Progress, Resolved and Closed, PILOTA stamps who resolved an item and when, and past-due items are flagged. You can assign items to your own team or to a subcontractor with punch-list access on that project, and the same list is shared by iOS, Android and the web portal, next to PILOTA QC inspections.

Frequently asked questions

A punch list is the list of work items that must be completed or corrected before a project, or a portion of it, is closed out. Under AIA A201-2017, the contractor prepares it when it considers the work substantially complete and submits it to the architect.

Under AIA A201-2017 the contractor prepares the punch list and submits it to the architect, who then inspects and can add items. In practice, trades, the GC, the owner and the architect all contribute items during walks.

The formal punch list is prepared at substantial completion. Many contractors also punch each area as it finishes, so the final list is short and items are fixed while trades are still on site.

Each punch list item should include a specific location, a description of what is wrong, the responsible trade, a named assignee, a priority, a due date and a photo, plus who resolved and verified it.

Not always. Final payment usually also depends on closeout items your contract requires, such as warranties, O&M manuals, as-built drawings and lien releases.