Documenting a construction delay means giving written notice within your contract's deadline and keeping a daily record of what was delayed, why, for how long and what it cost. The notice protects your right to a time extension or extra payment; the daily records prove it. Without both, a real delay can turn into liquidated damages or unpaid extended costs.
Updated 2026-11-17
Construction contracts commonly require written notice of a delay or claim within a set number of days, and missing that deadline can cost you the claim even when the delay was real. Find the notice clauses in your contract before the job starts and put the deadlines on a list the PM and superintendent both see.
The deadlines differ by contract. A few examples from widely used documents:
Who caused the delay decides what you can recover. Contracts and courts use different terms, but the usual sorting is by cause and responsibility.
A201 Section 8.3.1 is a good example of how a contract lists causes that can extend time: acts or neglect of the owner or architect, changes ordered in the work, labor disputes, fire, unusual delay in deliveries, unavoidable casualties, adverse weather documented as the contract requires, and other causes beyond the contractor's control. FAR 52.249-10 lists, among others, acts of the government, fires, floods, epidemics, strikes, unusually severe weather and certain subcontractor or supplier delays.
The daily report is the backbone of delay documentation. For each day the delay affects the job, record what work was planned, what actually happened, what stopped or slowed it, and the crews and equipment affected. Use the same wording every day so a reviewer can follow the delay from start to finish.
Weather delays get extra scrutiny, because some bad weather is expected on any job. A201 Section 15.1.6.2 says a claim for additional time based on adverse weather must be documented by data substantiating that the weather was abnormal for the period, could not have been reasonably anticipated, and had an adverse effect on the scheduled construction.
That takes two kinds of record. Your daily reports show the effect: which activities on the critical path could not proceed and why. Historical weather data shows the weather was abnormal; NOAA's Climate Data Online is a free archive of past daily and monthly temperature, precipitation and wind records searchable by station. Record weather on the daily report every day, including good days, so the comparison is easy.
A delay to work that has float is not the same as a delay to the completion date. To get a time extension, show which scheduled activities were affected and how that pushed the critical path. Keep the baseline schedule and every update, note the delay in the update for the period it happened, and compare planned and actual dates for the affected activities.
A201 Section 15.1.6.1 says a claim for additional time must include an estimate of cost and of the probable effect of delay on the progress of the work, and that in the case of a continuing delay, only one claim is necessary. Keep documenting each day until the delay ends.
Delay costs are hard to rebuild months later. Track them while they happen: idle crew hours, standby equipment, extended site overhead, extra trips and overtime to make up time. Code them to a separate cost code for that delay so they stay out of the base budget and can be pulled into a change order request or claim. Keep the time cards, rental invoices and receipts with the delay file.
Keep the notice letters, meeting minutes and emails about the delay in the same file. When the claim is reviewed, the reviewer will want to see a single, dated story from first notice to the last day of impact.
| To | The person and address your contract names for notices. |
|---|---|
| From | Company and authorized person. |
| Project and contract number | Match the contract. |
| Date of notice | And how it was delivered. |
| Contract clause | The notice or claim section you are giving notice under. |
| Date delay began | Or the date the condition was first recognized. |
| Description of the event | What happened, factually. |
| Work affected | Schedule activities, areas and trades. |
| Cause | As you understand it now, with references such as RFI or directive numbers. |
| Expected impact | Estimated days and cost, or a statement that they are not yet known. |
| Steps being taken | What you are doing to reduce the delay. |
| Reservation of rights | That you will submit time and cost details as they become known. |
| Attachments | Daily reports, photos, correspondence. |
| Signature | Authorized signer, name, title, date. |
On the PILOTA daily report, the day's weather fills in for the job's location, and each delay is logged with a category and hours lost alongside the crew, equipment and captioned photos for that day. Change orders record the days a change adds to the schedule next to its cost, and RFIs carry a needed-by date with overdue RFIs flagged. Reports can be shared as a PDF for the delay file.
Give written notice within the deadline in your contract, then record the delay every day it lasts: the cause, the activities affected, start and end times, hours lost, crews and equipment affected, photos, communications and costs.
It depends on your contract. AIA A201-2017 requires claims to be initiated within 21 days, FAR 52.249-10 requires written notice of excusable delay within 10 days on federal fixed-price construction, and other contracts set their own deadlines.
Show that the weather was abnormal for the period, that it could not have been reasonably anticipated, and that it affected scheduled work. Daily reports show the effect; historical weather data, such as NOAA's Climate Data Online, shows the weather was abnormal.
An excusable delay is caused by events outside the contractor's control and usually earns a time extension. A compensable delay is caused by the owner or its consultants and can earn both time and money, depending on the contract.
Under AIA A201-2017, no: in the case of a continuing delay only one claim is necessary. Keep documenting each day until the delay ends.